Timeline Week of 09/23/02: Project idea initial planning. Week of 09/30/02: Getting the proposal done. Getting the main circuit design. Week of 10/07/02: Gathering parts. Protocol development. On-site circuit design. Week of 10/14/02: Circuit verification and simulation. Program for the circuit writing. Week of 10/21/02: Making PCB card and card reader. Week of 10/28/02: Making fan dimmer and light controller circuit. Week of 11/04/02: Making controllable electronic device circuit. Modify electronic device. Week of 11/11/02: Integration of all circuit and the computer. Week of 11/18/02: Bug fixing and such. Week of 11/25/02: Final testing of circuit and debugging. |
|